← Model losses

Head-to-head comparison

claude-code-cli / claude-sonnet-5-5 / medium / medium effort preferred over openai / gpt-6-luna / none / none effort · close win.

Primary judge: Sol 6.1, requested Low. Effective provider effort and internal attempts were not verified. A close win is still a scored preference; it does not establish a material defect.

Reviewed public evidence

Task goal

Read-only planning analysis. TasksA andB start immediately and take2and4days. C takes3days afterA; D takes2days afterbothB andC; E takes1day afterD. Capacity permits all independent tasks in parallel. Find the earliest completion and critical path. A team proposes cuttingBby2days to save2days overall. Evaluate that claim and name a more useful reduction, including the smallest uncertainty/ownership checks before committing a deadline. No tools or executed-test claims. Three numbered items, under180words.

claude-code-cli / claude-sonnet-5-5 / medium / medium effort answer

1. **Schedule:** A finishes day 2 and C at day 5. B finishes day 4. D runs days 5-7 and E runs day 7-8. The earliest completion is **day 8**. The critical path is **A→C→D→E** (2+3+2+1). B has 1 day of float.

2. **The claim fails.** Cutting B by 2 days (4→2) saves **0 days**, because C still gates D at day 5. It only increases B's float to 3 days. The better reduction is on the critical chain.
   - Cutting D or E by 1 day saves a full day.
   - Cutting A or C by 1 day saves 1 day.
   - Cutting A+C by 2 days saves only 1 day, because B becomes critical at day 4. Saving 2 days needs the A/C cut of 2 plus B cut by 1, or a 2-day cut in D/E.

3. **Checks before committing a deadline:**
   - Name an owner for each of A, C, D and E.
   - Confirm each duration is an estimate with a range, and that B's slip beyond 1 day would make it critical.
   - Verify "parallel capacity" for A and B in practice, including people and environments.
   - Confirm there are no hidden dependencies and no handoff or review lag between C and D.
   - Confirm that D needs both B and C complete.

openai / gpt-6-luna / none / none effort answer

1. Earliest completion is **8 days**: A and B start at day 0; C finishes day 5, while B finishes day 4. D then finishes day 7, and E finishes day 8. Critical path: **A → C → D → E**.

2. Cutting B by 2 days does **not** save 2 days overall: B would finish at day 2, still before C at day 5, so completion remains day 8. B has 1 day of slack.

3. Reduce a task on the critical path: shortening A, C, D, or E by 1 day saves 1 day overall, assuming durations and dependencies hold. Before committing a deadline, confirm task durations and dependency/ownership handoffs—especially that D can start only after both B and C, and that the named owners can meet those dates.

Primary judge's stated reason

A receives a slight forced preference because its bottleneck-shift explanation helps avoid overpromising savings when selecting an alternative reduction. This is not an established material quality difference: B fully answers the core planning question, and an independent review could reasonably prefer its focused deadline checks.

This reason is the judge's assessment. No independent factual-defect finding is asserted by this record.

Battle wave: dd52f0cd-a901-4236-948d-93e82281c19b. Pair: brp1_302d17f06189717038d7f0c065ef84da32999db2d537372a799cb27bfb0df286. A separate independent review is required before calling a concern a verified factual defect. Judge disagreement is not recorded here.