Read-only planning analysis. A service has a monthly availability target99.9percent. A dashboard shows99.95percent for the first10days; the team proposes spending the remaining budget on a risky rollout. Traffic varies sharply byday, outages may be partial, and the dashboard excludes monitoring gaps. Explain the minimum evidence and decision gate for a staged rollout, including denominator, unknown intervals, rollback triggers and ownership. Avoid treating remaining calendar time as a known request budget. No tools or executed-test claims. Three numbered items, under180words.
claude-code-cli / claude-sonnet-5-5 / low / low effort answer
1. **Denominator and budget:** Define the SLI as good events over valid events, using request counts (or weighted partial-failure minutes) rather than calendar time. The 99.95% for 10 days is a rate, not remaining budget. Because traffic varies sharply, a quiet or busy day changes how much of the month's budget has been spent. Compute spend against the projected full-month request volume, with a stated range. Keep a reserve, and do not spend the whole remainder.
2. **Unknown intervals:** Treat monitoring gaps as unknown, not good. Report the gap duration, the traffic estimated from independent sources (load balancer or client logs), and a worst-case SLI with those intervals counted as failed. Gate the rollout on the worst case still leaving enough budget. Partial outages must count by failed fraction, not as binary up or down.
3. **Staged gate, triggers and ownership:** Roll out in small cohorts, each with a minimum sample size, a hold period and a named approver. Pre-agree automatic rollback triggers: a fast burn rate, an error rate above baseline, a latency breach, or a monitoring blind spot during the stage. The release owner executes rollback, the SRE or service owner owns the budget decision, and the on-call is notified. Record the evidence before each promotion.
claude-code-cli / claude-opus-5-5 / medium / medium effort answer
1. **Denominator and budget.** Recompute the SLI from request-weighted good and total events, not dashboard time. Count partial outages by the fraction of requests that failed. Remaining budget equals 0.1% of the *forecast* monthly total requests, minus bad requests so far. Traffic swings sharply by day, so the forecast is a range. Use its low bound. "Twenty days left" is not a request budget.
2. **Unknown intervals.** Excluded monitoring gaps are not good time. Measure each gap's duration and its likely traffic. Either count it as bad, or bound it with independent sources such as load-balancer logs or client telemetry. Recompute the 99.95% under that worst case. If little budget remains (illustrative threshold: under half), there is no rollout.
3. **Gate, rollback and ownership.** Stage the rollout as canary, then about 10%, about 50%, then full, with a hold at each stage. Roll back automatically on SLI breach, a fast burn-rate alert, or a stage using more than its preset slice of remaining budget. The rollback path must be rehearsed. One named rollout owner holds abort authority, and the SLO owner or on-call approves each stage. Pause if traffic forecasts or monitoring degrade.
Primary judge's stated reason
Forced, slight preference for B: its minimum-sample requirement makes the promotion gate somewhat more actionable under variable traffic. This is not an established material quality difference; an independent review could reasonably favor A's conservative forecast rule and rollback preparation.