openai / gpt-6-astra / low / low effort preferred over cursor / grok-4.7 / Grok 4.7 High / high effort · clear win.
Primary judge: Sol 6.1, requested Low. Effective provider effort and internal attempts were not verified. A close win is still a scored preference; it does not establish a material defect.
Reviewed public evidence
Task goal
Plan a six-week pilot of a shared equipment booking product for three departments. Evidence: 300 potential users; two designers and three developers available; budget fixed; current bookings live in spreadsheets; equipment managers must approve hazardous items; existing identity service supports login but no department roles; launch must preserve existing spreadsheet bookings; success means fewer double bookings and less manager coordination time, measured against a two-week baseline. Deliver scope and exclusions, dependency-aware weekly milestones, role and ownership model, migration and rollback plan, measurable pilot criteria and top five risks with mitigations. Show what you would defer if identity roles slip two weeks. Avoid inventing stakeholder approval or performance data. Self-contained read-only planning evaluation.
openai / gpt-6-astra / low / low effort answer
## Recommendation and evidence
Run a **six-week, tightly scoped pilot**, with a two-week baseline in weeks 1–2, controlled launch in week 4, and measurement through week 6. Support all three departments through a bounded equipment inventory; treat 300 users as the potential audience, not a confirmed adoption target.
Work was independent and read-only, using only the supplied evidence. Confidence is **moderate**: feasibility depends on spreadsheet quality, manager availability, and permission requirements not yet established.
## Scope and exclusions
**Include**
- Existing identity-service login.
- An application-owned, explicitly maintained department membership and equipment-manager assignment roster.
- Equipment availability, booking, cancellation, and hazardous-item approval.
- Server-side authorization and atomic conflict prevention for overlapping reservations.
- Audit history for booking changes, approvals, and permission changes.
- Spreadsheet migration preserving existing reservations.
- Simple measurement and operational reporting.
For hazardous equipment, a request must never become a confirmed booking without an authorized manager’s approval. Use a visible pending hold that blocks competing bookings; managers release or reject stale requests under a documented operating rule. Do not invent an approval expiry without understanding current practice.
**Exclude**
- Recurring-booking creation, complex waitlists, optimization, billing, procurement, maintenance scheduling, native mobile apps, and broad integrations.
- Automated identity-role synchronization if it threatens the critical path.
- Equipment whose existing bookings cannot be reconciled safely.
- New eligibility or safety-certification workflows unless existing rules make them mandatory; if mandatory, treat them as launch dependencies rather than silently omitting them.
Existing recurring spreadsheet reservations still need preservation, even if the pilot cannot create new series.
## Dependency-aware milestones
| Week | Deliverable and owner | Dependencies / gate |
|---|---|---|
| **1 — Discover and instrument** | Designer 1 maps booking and manager workflows; Designer 2 defines usability and accessibility checks. Developer 1 validates login and authorization options; Developer 2 defines booking/conflict model; Developer 3 inventories spreadsheets and prototypes import. Start baseline collection across all three departments. | Identify equipment owners, canonical spreadsheet sources, existing approval rules, measurement definitions, and an accountable pilot decision owner. These appointments are proposed, not confirmed. |
| **2 — Baseline and design freeze** | Finish two-week baseline. Agree scoped inventory and explicit roster. Complete prototype validation, import dry run, conflict-resolution list, and measurement instrumentation design. Developers build authentication, core schema, and transactional booking foundation. | Baseline must use the same definitions planned for the pilot. Membership and manager assignments need verification before access is enabled. |
| **3 — Integrated pilot candidate** | Complete booking/cancellation, hazardous holds and approval, authorization checks, audit events, import/export, and operational metrics. Designers run end-to-end usability checks; developers test concurrent bookings, unauthorized approval attempts, and migration reconciliation. | Login, verified roster, canonical equipment IDs, and reconciliation rules available. Unresolved legacy conflicts stay visible and block affected inventory. |
| **4 — Rehearse and launch** | Rehearse migration and rollback, train managers, then launch a small cohort spanning all three departments. Expand within the selected inventory only after reconciliation and workflow checks pass. | Authorized cutover decision; verified migration; working authorization and hazardous approval; tested restore/export; named support coverage. If a gate fails, delay affected scope rather than bypass it. |
| **5 — Stabilize and measure** | Expand participation within the 300-person audience as support capacity allows. Fix reliability and workflow defects; track booking conflicts, manager effort, pending requests, and adoption. | Avoid feature expansion that changes the comparison. Record cohort or inventory changes so results remain interpretable. |
| **6 — Evaluate and decide** | Compare pilot results with baseline, report uncertainty and departmental differences, document residual risks, and recommend continuation, revision, or rollback. | Enough comparable booking activity and manager-time observations. Otherwise report an inconclusive pilot and propose a bounded extension rather than claiming success. |
### Delivery ownership
- **Developer 1:** technical lead, login, authorization, deployment, rollback coordination.
- **Developer 2:** booking integrity, approval state machine, concurrency testing.
- **Developer 3:** migration, reconciliation, instrumentation, operational exports.
- **Designer 1:** product scope, workflows, manager onboarding.
- **Designer 2:** usability/accessibility, measurement materials, participant support design.
- **Equipment managers:** verify assigned equipment and legacy reservations; approve hazardous requests; record coordination time.
- **Department representatives:** validate membership and local operating rules.
- **Pilot decision owner, to be designated:** resolve scope trade-offs and make launch/continuation decisions within the fixed budget.
These responsibilities require operational participation beyond the five-person delivery team; that capacity is not established by the evidence.
## Permission model
| Role | Authority |
|---|---|
| Requester | View permitted equipment, request bookings, and cancel own bookings under existing rules. |
| Equipment manager | Review hazardous requests and administer bookings only for assigned equipment. |
| Pilot administrator | Maintain verified memberships and manager assignments, manage imports, and perform audited recovery operations. |
Bind permissions to stable identity IDs, not display names or email-domain guesses. Department membership must not automatically grant manager authority. Define cross-department equipment access explicitly. Enforce permissions in the service, not only the interface.
## Migration and rollback
1. **Inventory and snapshot:** identify all authoritative spreadsheets; preserve original files and source-row identifiers.
2. **Normalize and reconcile:** map equipment, users, dates, time zones, cancellations, recurring occurrences, and approval status. Never infer hazardous approval from the mere existence of a spreadsheet row.
3. **Handle existing conflicts:** retain every source record; flag overlapping legacy bookings and obtain operational resolution. Block new reservations on unresolved equipment.
4. **Dry-run import:** compare source and destination counts, reservation details, approval state, and unresolved exceptions. Managers verify their equipment records.
5. **Cut over:** freeze spreadsheet editing for a scheduled window, capture final changes, import, reconcile, and then make the application the booking authority. Keep spreadsheets as read-only archives. Use a logged intake queue during the freeze.
6. **Rollback triggers:** lost or altered reservations, authorization failures, hazardous confirmation without approval, or booking-integrity failures. Pause affected booking operations immediately.
7. **Rollback execution:** preserve the application audit log and export all post-cutover creations, changes, cancellations, holds, and approvals. Reconcile these into a recovery spreadsheet derived from the original snapshot. Verify it before reopening spreadsheet bookings; never simply restore a stale snapshot. Announce one authoritative booking channel and preserve incident evidence.
A rehearsed recovery procedure is a launch gate; achievable recovery time is unknown until rehearsal.
## Measurable pilot criteria
The thresholds below are **proposals**, not observed results or stakeholder-approved commitments. Settle them before pilot outcomes are visible.
| Measure | Definition and proposed criterion |
|---|---|
| Double bookings | Confirmed overlapping reservations for the same exclusive equipment per 100 confirmed reservations. Target **at least 50% reduction** against baseline; report raw counts and exposure alongside rates. |
| Manager coordination time | Minutes spent clarifying, scheduling, resolving conflicts, and chasing approvals per booking request, using the same logging method in both periods. Target **at least 25% reduction**; also report total weekly minutes. |
| Booking preservation | **100% of in-scope existing reservations accounted for**, with no silently dropped or altered reservations. Exceptions must be reconciled before affected inventory launches. |
| Safety and authorization | **Zero hazardous confirmations without recorded authorized approval; zero verified unauthorized manager actions.** |
| Evaluation coverage | Observations from all three departments using matched equipment and comparable booking activity. Set a minimum evidence volume after seeing baseline frequency, before pilot launch. Insufficient volume means inconclusive results. |
Report pending-request age, abandoned requests, use of off-system bookings, and user participation as guardrails: lower manager effort is not success if booking work simply stops. If baseline double bookings are zero, percentage reduction is undefined; report continued zero conflicts and acknowledge that reduction cannot be demonstrated.
## If identity roles slip two weeks
**Do not make identity-provider department roles the default critical path.** Existing login plus an audited, verified application roster can support the pilot if this authorization approach is permitted.
- Defer identity-role synchronization, automated provisioning/deprovisioning, self-service membership, and complex cross-department policies.
- Keep a small explicit roster spanning all three departments; review access changes manually.
- Reallocate integration effort to booking integrity, migration, and measurement rather than increasing budget.
- If centrally issued roles are mandatory, or the application roster is not permitted, restrict work to migration rehearsals, usability testing, and read-only previews until authorization is available. Delay transactional launch.
- A launch delayed to week 6 cannot credibly provide the planned observation window. Report readiness and limited early observations, then seek a separately authorized extension rather than claiming the six-week success criteria were met.
## Top five risks
| Risk | Mitigation |
|---|---|
| **1. Identity-role delay or incorrect privileges** | Validate permitted authorization architecture in week 1; use verified least-privilege assignments; test permission boundaries and revocation. |
| **2. Spreadsheet loss, ambiguity, or pre-existing conflicts** | Snapshot sources, preserve lineage, dry-run reconciliation, quarantine affected equipment, and rehearse delta-aware rollback. |
| **3. Concurrent bookings or unsafe approval transitions** | Atomic conflict enforcement, explicit reservation states, authorized approvals, and targeted concurrency/state-transition tests. |
| **4. Manager bottlenecks and spreadsheet workarounds** | Validate manager coverage, provide a clear pending queue, train users, establish one booking authority, and track off-system requests. |
| **5. Fixed-capacity delivery produces weak evaluation** | Bound equipment scope, freeze features, instrument early, preserve comparable measurement cohorts, and report uncertainty rather than overclaiming. |
## Alternatives and missing dependencies
A spreadsheet-front-end pilot could launch faster, but retaining multiple editable booking sources undermines conflict prevention. Full identity integration is preferable long term but introduces avoidable schedule coupling if local authorization is acceptable.
Unknowns include spreadsheet volume and quality, equipment exclusivity rules, hazardous-item eligibility requirements, manager coverage, identity integration constraints, hosting readiness, and baseline incident frequency. These determine achievable inventory scope and whether the six-week window can establish improvement.
**Next useful action:** hold a week-1 working session with representatives from all three departments and equipment managers to identify authoritative spreadsheets, verify approval/access rules, nominate operational owners, and start the two-week baseline immediately.
cursor / grok-4.7 / Grok 4.7 High / high effort answer
The six-week pilot should dual-run a single shared booking calendar beside the current spreadsheets. Login uses the existing identity service. Department roles stay off the critical path. Success is a lower double-booking rate and less manager coordination time in weeks 5–6 than in a frozen two-week spreadsheet baseline from weeks 1–2.
**Confidence:** medium on the dependency order, low on whether two designers and three developers can finish import, conflict checks, and fail-closed approval by week 4. No velocity, schema, identity contract, baseline counts, or budget figure is in the supplied evidence.
## 1. Recommendation
### Scope
- One shared equipment calendar for the three departments, covering only items already present in the spreadsheets.
- Login through the existing identity service, using the subject id only.
- Non-destructive import of current spreadsheet bookings so those intervals still occupy the calendar.
- Conflict check on the combined occupancy: imported rows plus pilot bookings.
- Hazardous items stay unconfirmed until an equipment manager approves. Unknown hazard class stays unconfirmed.
- A local approver allow-list of identity subject ids.
- A 14-day baseline while spreadsheet behavior is unchanged, then a 14-day live comparison in weeks 5–6.
- Daily reconciliation and a rehearsed export back to a spreadsheet.
### Exclusions
- Identity-service department roles, department-scoped permissions, and automatic approval routing from identity claims.
- Replacing or editing the original spreadsheet files.
- Extra departments, equipment types absent from the spreadsheets, native mobile apps, billing, maintenance, depreciation, and per-department custom calendars.
- Extra headcount or vendor spend. The budget figure is not in evidence, so the plan uses only the five people named.
- Any numeric success target. “Fewer” is the only success direction supplied. No baseline rate or duration is supplied.
### Dependency-aware weeks
Week 1 opens the baseline and does not change how people book. Freeze two definitions before counting starts: a double booking is two or more overlapping confirmed reservations for the same equipment item; coordination time is manager minutes spent resolving conflicts and arranging equipment, counted separately from minutes spent on required hazard approvals. Take a read-only spreadsheet copy, inventory columns and existing overlaps, and prove login returns a subject id. Design four states: preserved booking, conflict, pending approval, denied.
Week 2 ends the 14-day baseline and stores that record unchanged. Build import from the copy so original files stay untouched. Each imported row keeps a pointer to its spreadsheet row. Same equipment and overlapping times conflict. A pending hazardous request holds the slot so approval delay does not create a second confirmed booking.
Week 3 turns on authenticated use against imported occupancy. Non-hazardous requests confirm when the slot is free. Hazardous and unknown-class requests stay pending. Only an allow-listed manager can approve or deny. An empty allow-list blocks hazardous confirmation.
Week 4 is the launch gate. Re-import spreadsheet edits on a short interval, publish a diff, and rehearse rollback: disable new pilot writes and export pilot-originated bookings into a spreadsheet with the source columns. Go live in week 5 only if preservation, login, conflict checks, fail-closed hazard handling, and the rollback rehearsal are done. Identity department roles join this week only if the contract is already finished. Otherwise they wait until after week 6.
Weeks 5–6 are the comparison window for all three departments on the preserved equipment set. Count overlaps on the combined import plus pilot calendar, so bookings that remain only in a spreadsheet still count. On the last day, compare the two 14-day rates and the two coordination-time totals with booking volume reported beside them. If the baseline record is missing or the definitions changed, the result is inconclusive.
### Roles and ownership
- Designer 1 owns the booking and conflict flows and drafts the metric definitions. Designer 2 owns the approval-queue states and is backup for the calendar flows.
- Developer 1 owns import, reconciliation, and rollback export. Developer 2 owns the booking and conflict rules. Developer 3 owns login, the interim approver allow-list, and metric events. Each developer backs up one of the others.
- Equipment managers approve or deny hazardous requests and are the source of the hazard classification and the allow-list. Their identities are not in the evidence, so Developer 3 cannot fill that list alone.
- Identity-service owners own department roles. They are outside the five-person team.
- A single pilot decision owner is unfilled. One person must be named to freeze definitions, call the week-4 gate, and call the week-6 continue-or-roll-back read. None of the supplied roles covers that.
### Migration and rollback
Copy the spreadsheets at the start and import from the copy. Do not write to the original files. Keep re-importing later spreadsheet edits during the pilot so both channels reserve time. Pilot rows carry `source=pilot`; imported rows carry `source=spreadsheet`.
Rollback is the week-4 export plus a switch that stops pilot creates. Original spreadsheet rows remain in the original files. Pilot-originated rows survive only if the export ran. After rollback, the interim allow-list is unused. No identity-service data is changed, so there is nothing to undo there.
### Measurable pilot criteria
Compare weeks 5–6 with weeks 1–2.
- Double-booking rate: overlapping confirmed reservations divided by confirmed booking-days. Success is a lower rate. Report raw counts and total booking volume in both windows.
- Manager coordination minutes, using the week-1 definition. Success is a lower total. Report hazard-approval minutes separately and do not treat them as the success measure.
- Hard stops, each with a required count of zero: confirmed hazardous bookings with no approval record; original spreadsheet rows missing from the source files; active imported intervals missing from the calendar.
- Week-6 result is continue only when both rates are lower and every hard stop is zero. Otherwise roll back or record inconclusive. Do not fill in a percentage target. None was supplied.
### Top five risks and mitigations
1. The baseline is skipped or redefined after week 2, so the comparison is invalid. Freeze definitions in week 1 and store the week-2 record unchanged.
2. People keep booking in spreadsheets and the pilot, hiding overlaps. Re-import on a short interval and score doubles on the combined calendar.
3. A two-week identity-role slip is treated as a launch blocker and consumes the only comparison window. Roles are optional after week 4; the interim allow-list covers hazardous approval.
4. The approver allow-list is empty or hazard class is incomplete, so hazardous equipment cannot move. Collect manager subject ids and the hazard list before week 3. Unknown class stays pending.
5. Fixed people and fixed budget absorb per-department customization. Keep one calendar, the spreadsheet equipment set, and the week-4 cut line: if import or conflict checks are late, drop convenience filters before dropping preservation, conflict checks, or fail-closed approval.
### If identity roles slip two weeks
Assume the role contract was aimed at the week-4 gate and arrives around week 6. Leave it off through the comparison window so authorization does not change mid-measurement.
Defer identity department membership, identity equipment-manager claims, permission filtering by department, approval routing derived from those claims, and retirement of the local allow-list.
Keep login, the shared three-department calendar, department as a display label taken from the spreadsheet when that column exists, the local allow-list, spreadsheet re-import, rollback export, and both success measures. One shared pool is the fallback when the spreadsheets have no department field. Revisit identity roles only after the week-6 read, and only if the pilot continues.
## 2. Alternatives considered
Retiring the spreadsheets at launch fails the preservation requirement and leaves no rollback copy. Holding the pilot until department roles exist puts a non-critical dependency on the only two weeks that can be compared with the baseline. Leaving a pending hazardous request unheld frees the equipment sooner and recreates the double-booking failure the pilot is scored on. Separate calendars per department exceed the fixed five-person capacity. Manager satisfaction as the success measure would replace the two outcomes the pilot is required to use.
A lower double-booking rate is a weak result if confirmed booking volume collapses, because people may have left both channels. Publish volume next to the rate.
## 3. Missing evidence and consequences
These are absent from the supplied evidence: spreadsheet columns, row counts, editors, and overlap grain; the hazard list and current approval path; manager subject ids; the identity login contract and any real role delivery date; baseline counts and coordination minutes; the budget amount; equipment counts; whether all 300 people are in the three departments. Until a read-only spreadsheet sample and a login spike exist, weeks 2–4 stay conditional. An empty manager allow-list blocks hazardous confirmation. A missed week-1 baseline makes week 6 inconclusive. No decision owner means the week-4 gate and the week-6 read have no named caller.
## 4. Next useful action
Freeze the two metric definitions and start the 14-day spreadsheet baseline now, in parallel with a read-only schema sample and a login subject-id spike. Collect the hazardous-item list and approver subject ids before any pilot create is enabled.
Primary judge's stated reason
A is preferred because its migration design more directly supports fewer double bookings while preserving legacy reservations. Its rollback also explicitly reconciles post-cutover changes, cancellations, holds, and approvals before reopening spreadsheets, whereas B describes exporting pilot-originated bookings without comparable reconciliation detail. Together these constitute a supported practical advantage in booking continuity, not a claim that either plan has been executed or proven successful.
This reason is the judge's assessment. No independent factual-defect finding is asserted by this record.
Battle wave: ebca1385-ed0b-4cca-a716-308a4a3f0509. Pair: brp1_e5255f40616028d589d90254e9beb25de941169034f8a538230038e80897555a. A separate independent review is required before calling a concern a verified factual defect. Judge disagreement is not recorded here.